Subprocess expiration

Written by Kestutis Vansavicius

One of the primary purposes of Daymi is to provide clients with a complete audit trail, containing a detailed history of all their processes.
​

To support compliance regulations and maintain a reliable record of historical actions, we've ensured that users cannot change the state of processes after a specified period, which can be set by each organization.

Default configuration

By default, it's not possible to change the status of a subprocess that has passed its active period:

  • Daily processes: 7 days after the deadline

  • Weekly/Bi-weekly: 14 days

  • Monthly/Bi-monthly: 60 days

  • Quarterly: 180 days

  • Yearly: 365 days

One-time or ad hoc processes don't have these restrictions.


Custom expiration term

We can adjust these rules to allow users to change the status of a subprocess for an extended period, enabling status changes beyond the usual timeframe.
​

If you'd like us to configure this setting for your organization, please contact us, and we’ll set up the new rules. Note: These adjustments will apply to all processes according to the rules you specify.

  • Configuration can only be changed by the Support team at Daymi, shoot us an e-mail at [email protected] 📧.

  • Provide us with a number of calendar days to extend the deadline term with (consider the optimal number of days, including weekends and holidays).

  • Expiration cannot be applied to Once frequency processes since you can always change their status.